25 CFR § 1000.1440 — § 1000.1440 What constitutes a “significant change” in the original scope of work?
Beta. Legal information, not legal advice. LEGALDIGM is not a law firm. Check the official source for the current text.
Analyze this law with AI§ 1000.1440 What constitutes a “significant change” in the original scope of work?
A significant change in the original scope of work is:
(a) A change that would result in a cost that exceeds the total of the Federal project funds available and the Tribe's/Consortium's contingency funds; or
(b) A material departure from the original scope of work, including substantial departure from timelines negotiated in the construction project agreement.