Beta
23 CFR § 661.41
23 CFR § 661.41 — § 661.41 After a bridge project has been completed (either PE or construction) what happens with the excess or surplus funding?
Beta. Legal information, not legal advice. LEGALDIGM is not a law firm. Check the official source for the current text.
Analyze this law with AI§ 661.41 After a bridge project has been completed (either PE or construction) what happens with the excess or surplus funding?
Since the funding is project specific, once a bridge design or construction project has been completed under this program, any excess or surplus funding is returned to FHWA for use on additional approved TTF bridge projects.