23 CFR § 661.39 — § 661.39 How are project cost overruns funded?
Beta. Legal information, not legal advice. LEGALDIGM is not a law firm. Check the official source for the current text.
Analyze this law with AI§ 661.39 How are project cost overruns funded?
(a) A request for additional TTFBP funds for cost overruns on a specific bridge project must be submitted to Bureau of Indian Affairs Division of Transportation (BIADOT) and FHWA for approval. The written submission must include a justification, an explanation as to why the overrun occurred, and the amount of additional funding required with supporting cost data. If approved by FHWA and BIADOT, the request will be placed at the top of the appropriate queue (with a contract modification request having a higher priority than a request for additional funds for a project award) and funding may be provided if available.
(b) Project cost overruns may also be funded out of the Tribe's regular TTP construction funding.