18 CFR § 430.13 — § 430.13 Protected area permits for new withdrawals.
Beta. Legal information, not legal advice. LEGALDIGM is not a law firm. Check the official source for the current text.
Analyze this law with AI§ 430.13 Protected area permits for new withdrawals.
Any person, firm, corporation or other entity who proposes to develop a new ground water withdrawal or expand an existing ground water withdrawal for any purpose within the Southeastern Pennsylvania Ground Water Protected Area shall be required to obtain a protected area permit under this regulation if the proposed new or increased rate of withdrawal from a well or group of wells operated as a system average more than 10,000 gallons per day over a 30-day period. Whenever the Executive Director, upon investigation or upon a reference from a state or federal agency, determines that a new or increased withdrawal from a group of wells within the protected area, whether or not such wells are operated as a system, may have a substantial effect on the water resources of the basin or is likely to have a significant adverse effect on other water uses within the protected area, the Commission may direct a notice to the owners or sponsors of such wells, and require such owners or sponsors to apply for and obtain a protected area permit under this regulation.
(a) Applications for a protected area permit shall be submitted to the Commission on forms approved by the Executive Director. Each application shall be accompanied by the following information:
(1) A map indicating the location of existing wells and perennial streams.
(2) A written report prepared by a hydrogeologist describing the expected effects of the proposed withdrawal on existing wells, flows of perennial streams and the long-term lowering of ground water levels.
(3) A log showing the nature of subsurface material encountered during the construction and installation of the exploratory or production well(s).
(4) The detailed results of extended pump tests, of not less than 48 hours duration, and records of observations during such pump tests from representative monitoring wells.
(b) Applications for a protected area permits whose daily average withdrawal during any calendar month is in excess of 10,000 gallons shall be accompanied by an application fee of $100. Government agencies shall be exempt from such application fee.
(c) If the application for a protected area permit is for a daily average withdrawal during any calendar month in excess of 100,000 gallons, it shall be accompanied by such other information or exhibits required by Article 3 of the Commission's Rules of Practice and Procedure. In such cases, only the application fee required by the Rules will be assessed.
(d) To qualify for approval of a protected area permit, the owner or sponsor of the proposed withdrawal shall demonstrate that:
(1) The proposed withdrawal is consistent with the Commission's Comprehensive Plan and the policies and purposes of these regulations.
(2) Opportunities to satisy water requirements on a timely basis from existing available supplies and facilities have been explored and found infeasible.
(3) The proposed withdrawal, in conjunction with other withdrawals in the applicable ground water basin, will not exceed withdrawal limits of a ground water basin, aquifer or aquifer system.
(4) The proposed withdrawal will not significantly impair or reduce the flow of perennial streams in the area.
(5) Existing ground and surface water withdrawals will not be adversely impacted, or will be otherwise assured of adequate supplies in accordance with the requirements of § 430.19 of this part.
(6) The proposed withdrawal will not cause substantial, permanent adverse impact to the overlying environment.
(7) The owner or sponsor has adopted and will implement conservation and management programs as required by § 430.15 of this part.
(e) Ground water withdrawals for space heating or cooling purposes that are less than 100,000 gallons per day shall be exempt from obtaining a protected area permit provided that the water withdrawn is returned locally, and to the same ground water basin and aquifer system from which it is withdrawn, undiminished in quantity and quality (except temperature). Ground water withdrawals for space heating or cooling that are subsequently used for commercial or industrial water supply purposes are subject to Commission withdrawal and wastewater discharge regulations. Ground water withdrawals exempted pursuant to this subsection shall be subject to the registration requirements of § 430.17.
(f) All ground water withdrawal projects exempted by subsection “e” above shall be constructed in conformance with accepted industry practice and as a minimum shall comply with the following standards:
(1) All wells shall be drilled by a Pennsylvania licensed well driller and a Water Well Inventory Report shall be completed and filed with the Pennsylvania Department of Environmental Resources (PADER);
(2) No wells shall be located within a 100-year floodway;
(3) All wells shall have top of casing extended a minimum of one foot above the 100-year flood elevation;
(4) All wells shall have the casing protruding a minimum of six inches above the immediate surrounding grade;
(5) The area around all wells or well pits shall be constructed and/or graded to prevent the entrance of surface waters;
(6) All wells shall be accessible for inspection and shall have an access hole for water level measurements;
(7) In order to protect against significant leaks of refrigerant, all ground water heat pump systems shall be equipped with an automatic shutdown device that senses abnormally low or abnormally high refrigerant pressures;
(8) Any drilled well holes that are abandoned shall be sealed with a minimum of ten feet of cement grout. Additional seals may be required to separate different water-bearing zones.
(g) Protected area permits shall be approved or disapproved by the Executive Director with the concurrence of the Pennsylvania member of the Commission or his alternate.
(h) Dockets and protected area permits may be issued for a duration of up to ten years and shall specify the maximum total withdrawals that must not be exceeded during any consecutive 30-day period. Such maximum total withdrawals shall be based on demands projected to occur during the duration of the docket or protected area permit.
(i) Ground water withdrawal limits shall be defined for subbasins in accordance with the provisions of (i)(1) or (2) of this section. The limits for specific subbasins are set forth in (i)(3) of this section.
(1) Baseflow frequency analyses shall be conducted for all subbasins in the Southeastern Pennsylvania Ground Water Protected Area. The analyses shall determine the 1-year-in-25 average annual baseflow rate. The 1-year-in-25 average annual baseflow rate shall serve as the maximum withdrawal limit for net annual ground water withdrawals for subbasins. If net annual ground water withdrawals exceed 75 percent of this rate for a subbasin, such a subbasin shall be deemed “potentially stressed.” The Commission shall maintain a current list of net annual ground water withdrawals for all subbasins. “Net” annual ground water withdrawals includes total ground water withdrawals less total water returned to the ground water system of the same subbasin.
(2) Upon application by the appropriate governmental body or bodies, the withdrawal limits criteria set forth in (i)(1) of this section may be revised by the Commission to provide additional protection for any subbasin identified in (i)(3) of this section with streams or stream segments designated by the Commonwealth of Pennsylvania as either “high quality,” or “exceptional value,” or “wild,” or “scenic,” or “pastoral,” or to correspond with more stringent requirements in integrated resource plans adopted and implemented by all municipalities within a subbasin identified in (i)(3) of this section. Integrated resource plans shall be developed according to sound principles of hydrology. Such plans shall at a minimum assess water resources and existing uses of water; estimate future water demands and resource requirements; evaluate supply-side and demand-side alternatives to meet water withdrawal needs; assess options for wastewater discharge to subsurface formations and streams; consider stormwater and floodplain management; assess the capacity of the subbasin to meet present and future demands for withdrawal and nonwithdrawal uses such as instream flows; identify potential conflicts and problems; incorporate public participation; and outline plans and programs including land use ordinances to resolve conflicts and meet needs. Integrated resource plans shall be adopted and implemented by all municipalities within a subbasin and incorporated into each municipality's Comprehensive Plan.
(3)(i) The potentially stressed levels and withdrawal limits for all delineated basins and subbasins are set forth below:
Subbasin
Potentially Stressed (mgy) 1
Withdrawal Limit (mgy)
Neshaminy Creek Basin
West Branch Neshaminy Creek Basin
1054
1405
Pine Run Basin
596
795
North Branch Neshaminy Creek
853
1131
Doylestown Subbasin Neshaminy Creek
710
946
Warwick Subbasin Neshaminy Creek
889
1185
Warrington Subbasin Little Neshaminy Creek
505
673
Park Creek Basin
582
776
Warminster Subbasin Little Neshaminy Creek
1016
1355
Mill Creek Basin
1174
1565
Northampton Subbasin Neshaminy Creek
596
794
Newtown Creek
298
397
Core Creek Basin
494
658
Ironworks Creek Basin
326
434
Schuylkill River Basin
3026
4034
Lower Section Subbasin Neshaminy Creek
Hay Creek
974
1299
Lower Reach Manatawny-Ironstone Creek
1811
2414
Pigeon Creek
611
815
Schuylkill-Crow Creek
1157
1543
Schuylkill-Mingo Creek
671
895
Schuylkill-Plymouth-Mill Creeks
4446
5929
Schuylkill-Sixpenny Creek
1490
1987
Schuylkill-Sprogels Run
1091
1455
Schuylkill-Stony Creek
687
916
Schuylkill-Trout Creek
1082
1443
Stony Creek
1242
1655
Valley Creek
1865
2486
French and Pickering Creek Subbasins
Lower Reach French Creek
634
845
Lower Reach Pickering Creek
1716
2288
Middle Reach French Creek
1608
2145
South Branch French Creek
1044
1393
Upper Reach French Creek
1295
1726
Upper Reach Pickering Creek
1358
1811
Perkiomen and Skippack Creek Subbasins
East Branch Perkiomen-Indian Creeks
633
844
East Branch Perkiomen-Mill Creeks
720
961
East Branch Perkiomen-Morris Run
1214
1619
Hosensack-Indian Creeks
1257
1676
Lower Reach Skippack Creek
1069
1426
Perkiomen-Deep Creeks
1047
1396
Perkiomen-Lodal Creeks
1200
1600
Perkiomen-Macoby Creek
1252
1669
Swamp-Middle Creeks
1423
1898
Swamp-Minister Creeks
547
730
Swamp-Scioto Creeks
746
994
Towamencin Creek
466
622
Unami-Licking Creeks
992
1322
Unami-Ridge Valley Creeks
1068
1424
Upper Reach Perkiomen Creek
1223
1631
Upper Reach Skippack Creek
813
1084
West Branch Perkiomen Creek
1566
2088
Delaware River Basin
Jericho Creek
421
562
Mill Creek
1600
2134
Paunnacussing Creek
513
684
Pidcock Creek
563
751
Upper Reach Cobbs Creek
871
1161
Upper Reach Crum Creek
1290
1721
Upper Reach Darby Creek
1625
2167
Upper Reach East Branch Chester Creek
1865
2487
Upper Reach Frankford Creek
1414
1886
Upper Reach Poquessing Creek
1008
1344
Upper Reach Ridley Creek
1707
2275
Tohickon Subbasin
Tohickon-Beaver-Morgan Creeks
1156
1541
Tohickon-Deep Run
956
1274
Tohickon-Geddes-Cabin Runs
602
803
Tohickon-Lake Nockamixon
556
741
Tohickon-Three Mile Run
726
968
Pennypack and Wissahickon Subbasins
Lower Reach Wissahickon Creek
2750
3666
Upper Reach Wissahickon Creek
1302
1736
Middle Reach Pennypack Creek
1295
1727
Upper Reach Pennypack Creek
1358
1811
Brandywine Creek Subbasin
East Branch Brandywine-Taylor Run
1054
1405
Middle Reach Brandywine Creek
823
1098
Upper Reach Brandywine Creek
1614
2153
West Branch Brandywine-Beaver Run
2110
2813
West Branch Brandywine-Broad Run
2380
3173
West Valley Creek
1673
2231
Lehigh Subbasin
Upper Reach Saucon Creek
946
1262
1 mgy means million gallons per year.
(ii) Subject to public notice and hearing, this section may be updated or revised based upon new and evolving information on hydrology and streamflow and ground water monitoring or in accordance with paragraph (i)(2) of this section.
(j) Upon its determination that a subbasin is potentially stressed, the Commission shall notify all ground water users in the subbasin withdrawing 10,000 gallons per day or more during any 30-day period of its determination. If any such users have not obtained a docket or protected area permit from the Commission, they shall be required to apply to the Commission within 60 days of notification.
(k) In potentially stressed subbasins, dockets and protected area permit applications for new or expanded ground water withdrawals must include one or more programs to mitigate the adverse impacts of the new or expanded ground water withdrawal. The eligible programs are noted below. If the remainder of the application and the program(s) submitted are acceptable, the withdrawal may be approved by the Commission for an initial three-year period. The applicant shall implement the program(s) immediately upon Commission approval. If after the three-year period the program(s) is deemed successful by the Commission, the docket or permit duration may be extended for up to 10 years. The project sponsor shall be required to continue the program(s) for the duration of the docket or permit.
(1) A conjunctive use program that demonstrates the applicant's capability to obtain at least 15 percent of its average annual system usage from a reliable surface water supply. An acceptable program shall include either reservoir storage or an interconnection with a surface water supplier and an agreement or contract to purchase water from the supplier for the duration of the docket or permit.
(2) A water conservation program that exceeds the requirements of § 430.15. For existing water utilities, the program shall reduce average annual per capita water usage by at least five percent. All conservation programs shall include water conservation pricing, either inclining block rates, seasonal rates, or excess-use surcharges, and plumbing fixture rebate or retrofit components. For self-supplied users, the program shall include water efficient technologies such as recycling, reuse, xeriscaping, drip or micro irrigation, or other innovative technology approved by the Commission.
(3) A program to monitor and control ground water infiltration to the receiving sewer system. The program must quantify ground water infiltration to the system and document reductions in infiltration. The program should include such measures as leakage surveys of sewer mains, metering of sewer flows in mains and interceptors, analysis of sewer system flows to quantify infiltration, and remedial measures such as repair of leaks and joints, main lining, and main replacement.
(4) An artificial recharge or spray irrigation program that demonstrates a return of at least 60 percent of the total new or expanded annual withdrawal to the same ground water basin and aquifer system from which it is withdrawn. The program shall not impair ground water quality.
(5) An alternative program approved by the Commission to mitigate the adverse impacts of the new or expanded ground water withdrawal.
(l) The durations of all existing dockets and protected area permits may be extended by the Commission for an additional five years if the docket or permit holder successfully implements in either (k)(1) or (k)(2) of this section. If the docket or permit holder successfully implements both options, the docket or permit may be extended for an additional ten years. The Executive Director shall notify all docket and permit holders potentially affected by this resolution of their right to file an application to determine their eligibility for extension.
(m) It is the policy of the Commission to prevent, to the extent reasonably possible, net annual ground water withdrawals from exceeding the maximum withdrawal limit. An application for a proposed new or expanded ground water withdrawal that would result in net annual ground water withdrawals exceeding the maximum withdrawal limit established in paragraph (i)(3) of this section shall set forth the applicant's proposal for complying with the Commission's policy, with such supporting documentation as may be required by the Executive Director. Notification of the application shall be given to all affected existing water users who may also submit comments or recommendations for consideration by the Commission on the pending application. In taking action upon the application, the Commission shall give consideration to the submissions from the applicant and affected water users. If the Commission determines that it is in the public interest to do so, it may reduce the total of proposed and existing ground water withdrawals within a subbasin to a level at or below the withdrawal limit. Unless otherwise determined by the Commission, docket and permit holders shall share equitably in such reductions.
[46 FR 24, Jan. 2, 1981, as amended at 50 FR 5973, Feb. 13, 1985; 63 FR 6477, Feb. 9, 1998; 64 FR 35566, July 1, 1999]