Analyze this law with AITHE PAKISTAN WATER AND POWER DEVELOPMENT
AUTHORITY ACT, 1958
CONTENTS
CHAPTER I
PRELIMINARY
1.
Short title and extent
2.
Definitions
CHAPTER II
CONSTITUTION OF THE AUTHORITY
3.
Constitution of the Authority
4.
Appointment and term of office of Chairman and Members
5.
Remuneration and conditions of service
6.
Removal of Chairman or Members
7.
Meetings of the Authority
CHAPTER III
POWERS AND DUTIES OF THE AUTHORITY
8.
General powers and duties of the Authority and framing of schemes
9.
Schemes framed by other agencies
9A.
10.
Survey and experiments
10-A.
11.
Control over waters, power houses and grids
12.
Authority to have powers and obligations of licensee under Act IX of 1910
13.
Powers regarding certain matters
14.
Right of entry
15.
Sanction of the Government
16.
Arrangements with local body or other agency
CHAPTER IV
ESTABLISHMENT
17.
Employment of officers and servants
17A.
Omitted
18.
Recruitment and conditions of service and disciplinary powers
19.
Immunity of the Authority and its employees
20.
Delegation of powers to Chairman, etc.
CHAPTER V
REPORTS AND STATEMENTS
21.
Submission of yearly reports and returns, etc.
CHAPTER VI
FINANCE
22.
Authority Fund
23.
Authority to be deemed to be a local authority
24.
Limited liability
25.
Rates for sale of power
26.
Maintenance of accounts
27.
Annual statement of accounts
28.
Audit
CHAPTER VII
29.
Regulations
30.
Repeal
THE 1[PAKISTAN] WATER AND POWER DEVELOPMENT
AUTHORITY ACT, 1958
WEST PAKISTAN ACT NO. XXXI OF1958
[19th April, 1958]
AN
ACT
to provide for the unified and co-ordinated development of the water and power resources of
[Pakistan].
Preamble. WHEREAS it is expedient to provide for the unified and co-ordinated development
of the water and power resources of 3[Pakistan];
It is hereby enacted as follows:CHAPTER I
PRELIMINARY
1. Short title and extent. (1) This Act may be called the 4[Pakistan Water and Power
Development Authority Act, 1958].
(2) It extends to the whole of 5[Pakistan, except the 6[Districts] of Karachi.]
2. Definitions. In this Act, unless there is anything repugnant in the subject or context—
(i)
“Authority” means the 7[Pakistan Water and Power Development Authority]
established under section 3 of this Act;
(ii)
“Chairman” means the Chairman of the Water and Power Development
Authority;
(iii)
“controlled station” means a power generating station declared as a controlled
station under clause (iv) of sub-section (1) of section 11;
(iv)
“Government” means the 8[Federal Government];
(v)
“land” includes benefits to arise out of land, and things attached to the earth or
permanently fastened to anything attached to the earth;
(vi)
“local body” means any District Board, District Local Board, Municipal
Corporation, Municipal Committee, Municipality, Small Town Committee or
Notified Area Committee;
Substituted by West Pakistan Ordinance No. LXXII of 1979, s. 2.
Substituted by West Pakistan Ordinance No. LXXII of 1979, s. 2.
Substituted by West Pakistan Ordinance No. LXXII of 1979, s. 2.
Substituted by West Pakistan Ordinance No. LXXII of 1979, s. 3.
Substituted by the Federal Adaptation of Laws Order, 1975 (President’s Order No. 4 of 1975), Art. 2 and Sch.
Substituted by Act No. XIII of 1994, s. 2.
Substituted by West Pakistan Ordinance No. LXXII of 1979, s. 4.
Substituted by the Federal Adaptation of Laws Order, 1975 (President’s Order No. 4 of 1975), Art. 2 and Sch.
(vii)
“Member” means Member of the Water and Power Development Authority;
(viii)
“power” includes hydraulic power, electrical energy, steam, gas or any other
power notified as such by the 1[Government] in the Official Gazette; and
(ix)
“Regulations” means Regulations framed under this Act.
CHAPTER II
CONSTITUTION OF THE AUTHORITY
3. Constitution of the Authority. (1) There shall be established an Authority to be known as
the [Pakistan Water and Power Development Authority] for carrying out the purposes of this Act.
(2) The Authority shall be a body corporate, shall be entitled to acquire 3[, hold and dispose of]
property, shall have perpetual succession and a common seal and shall by the said name sue and be
sued.
4. Appointment and term of office of Chairman and Members. 4[(1) The Authority shall
consist of a Chairman and not more than three members, to be appointed by Government.]
(2) The term of office of the Chairman shall be five years and that of a Member three years.
(3) Any person ceasing to be the Chairman or Member by reason of the expiry of the term of
his office shall be eligible for re-appointment for another term or for such shorter term as the
Government may decide.
(4) The Chairman or any Member may at any time resign; provided that his resignation shall
not take effect until accepted by the Government.
5. Remuneration and conditions of service. The Chairman and each Member shall receive
such salary and allowances and be subject to such conditions of service as may be prescribed by the
Government, and shall perform such duties as are assigned to them under this Act or by any Regulation
framed under it.
6. Removal of Chairman or Members. The Government may by notification remove the
Chairman or any Member__
(a)
if he refuses or fails to discharge or becomes in the opinion of the Government,
incapable of discharging, his responsibilities under this Act; or
(b)
if he has been declared insolvent; or
(c)
if he has been declared to be disqualified for employment in, or has been
dismissed from the service of Pakistan, or has been convicted of an offence
involving moral turpitude; or
(d)
if he has knowingly acquired or continued to hold without the permission in
writing of the Government, directly or indirectly or through a partner, any share
Substituted by the Federal Adaptation of Laws Order, 1975 (President’s Order No. 4 of 1975), Art. 2 and Sch.
Substituted by West Pakistan Ordinance No. LXXII of 1979, s. 3.
Substituted by Act No. XIII of 1994, s. 3.
Substituted by the West Pakistan Ordinance No. XII of 1967, s. 2.
or interest in any contract or employment with or by or on behalf of the
Authority, or in any land or property which, in his knowledge, is likely to benefit
or has benefited as a result of the operation of the Authority.
7. Meetings of the Authority. (1) The Authority shall meet at such time and place and in such
manner, as may be prescribed by Regulations:
Provided that until Regulations are made in this behalf, such meetings shall be convened by
the Chairman.
(2) The Chairman, or in his absence a Member authorised by him, and one other Member shall
be present to constitute a quorum at a meeting of the Authority.
CHAPTER III
POWERS AND DUTIES OF THE AUTHORITY
8. General powers and duties of the Authority and framing of schemes. (1) The Authority
shall prepare, for the approval of the Government, a comprehensive plan for the development and
utilization of the water and power resources of 1[Pakistan] on a unified and multi-purpose basis.
(2) The Authority may frame a scheme or schemes for 2[a Province] or any part thereof
providing for all or any of the following matters, namely—
(i)
irrigation, water-supply and drainage; and recreational use of water resources;
(ii)
the generation, transmission and distribution of power; and the construction,
maintenance and operation of power houses and grids;
(iii)
flood control;
(iv)
the prevention of waterlogging and reclamation of waterlogged and salted lands;
(v)
inland navigation; 3[*]
(vi)
the prevention of any ill-effects on public health resulting from the operations
of the Authority ; 4[;] 5[and]
[(vii) Privatise or otherwise restructure any operation of the Authority except the
hydel generating power stations and the National Transmission Grid]
(3) Every scheme prepared by the Authority under sub-section (2) shall be submitted for
approval to the Government, with the following information:__
(i)
a description of the scheme and the manner of its execution;
_________________________________________________________________________________
Substituted by the Federal Adaptation of Laws Order, 1975 (President’s Order No. 4 of 1975), Art. 2 and Sch.
Substituted by the Federal Adaptation of Laws Order, 1975 (President’s Order No. 4 of 1975), Art. 2 and Sch.
Omitted by Act No. XIII of 1994, s. 4.
Substituted by Act No. XIII of 1994, s. 4.
Added by Act No. XIII of 1994, s. 4.
(ii)
an estimate of costs and benefits; the allocation of costs to the various purposes
to be served by the scheme and the amounts to be repaid by the beneficiaries;
and
(iii)
a statement of the proposals by the Authority for the resettlement or rehousing
of persons likely to be displaced by the execution of the scheme.
(4) The Government may sanction or may refuse to sanction, or may return for reconsideration
any scheme submitted to it under this section, or may call for such further details or information about
the scheme, or may direct such further examination of the scheme as it may consider necessary.
[(5) Where a scheme is sanctioned by the Government under sub-section (4), the Authority
__
may
(a)
undertake any joint venture or work in association with the Provincial
Government, an agency, corporation, company, authority or any person and
may subscribe to the equities and acquire such other rights and obligations as
may be necessary for such joint venture or association;
(b)
promote, form or sponsor any company or companies having objects of
installation of thermal and hydel projects and development and utilization of
any resources of energy for generation, transmission and distribution of power
and for survey, investigation, exploitation and utilization of resources of energy
for generation, transmission and distribution of power;
(c)
subscribe for, take or otherwise acquire, hold and dispose of shares, bonds,
debentures, commercial papers or other securities of any company promoted,
formed or sponsored under clause (b) and receive dividends or other payments
therefrom and transfer to it any of its land or any other property, moveable or
immoveable, tangible or intangible, against cash, shares, bonds, debentures,
commercial papers or other securities as is desirable or necessary to enable it to
privatise or otherwise restructure any operation of the Authority;
(d)
enter into any of the following arrangements which may be consistent with its
objects, namely:__
(e)
(i)
provision of services and personnel;
(ii)
provision of goods, appliances, plants, machinery and other material;
and
(iii)
purchasing of electrical capacity and energy from any company
specified in clause (b); and
enter into any contract or agreement with any company or companies specified
in clause (b).
Explanation.__ For the purpose of this section, the expression “privatise” means the transfer or
disinvestment of any of its assets, property, rights or liabilities, interest, power houses, grid operation
of work, or maintenance thereof, or generation or its distribution, by the Authority, with the prior
Added by Act No. XIII of 1994, s. 4.
approval of the Federal Government, for valuable consideration to any person, company or
body on ownership basis or for management, control, operation or maintenance, either in joint venture
or in association or otherwise and subject to such conditions as the Authority may impose.]
9. Schemes framed by other agencies. (1) Any scheme framed by an agency in 1[any
Province], other than the Authority, in respect of any of the matters enumerated in sub-section (2) of
section 8, if its estimated cost exceeds the amount to be prescribed by the Government, shall be
submitted to the Government through the Authority and the Government may pass any of the orders
contemplated by sub-section (4) of section 8.
(2) The Authority may, with the approval of the Government undertake the execution of any
scheme, or exercise technical supervision and administrative and financial control over the execution
of any scheme framed or sponsored by any agency in respect of the matters enumerated in sub-section
(2) of section 8.
[9A. Notwithstanding anything contained in this Act, the Authority may, with the previous
approval of the Government, undertake the execution of any scheme framed or sponsored by a
Provincial Government or any agency under the control of a Provincial Government or exercise
technical supervision and administrative and financial control over the execution thereof on such terms
and conditions as may be agreed to by the Authority on the one hand and the Provincial Government
or, as the case may be, such agency in consultation with the Provincial Government on the other.]
10. Survey and experiments. The Authority, if it considers this necessary or expedient for
carrying out the purposes of this Act, may__
(a)
cause studies, surveys, experiments or technical research to be made; or
(b)
contribute towards the cost of any such studies, surveys, experiments or
technical research made by any other agency.
[10-A. On and from such date as the Government may, by notification, declare and subject to
such terms and conditions as it may determine, all assets including lands, works, machinery, apparatus,
material and plants vested in the Government in the Electricity Department shall vest in the Authority,
and all liabilities in respect of the said assets shall be the liability of the Authority.]
11. Control over waters, power houses and grids. (1) Subject to the provisions of any other
law for the time being in force, the Authority__
(i)
shall have control over the—
(a)
underground water resources of any region in 4[a Province];
(b)
operation of 5[its] power houses and grids, including such ancillary
works as may be considered necessary for their proper operation;
Substituted by the Federal Adaptation of Laws Order, 1975 (President’s Order No. 4 of 1975), Art. 2 and Sch.
Substituted by the Federal Adaptation of Laws Order, 1975 (President’s Order No. 4 of 1975), Art. 2 and Sch.
Added by the West Pakistan Ordinance No. XIII of 1959, s. 3.
Substituted by the Federal Adaptation of Laws Order, 1975 (President’s Order No. 4 of 1975), Art. 2 and Sch.
Substituted by Act No. XIII of 1994, s. 5.
(ii)
(iii)
may make recommendations to the Government for prescribing standards for
the__
(a
operation and maintenance of all irrigation works;
(b)
maintenance of power houses and grids;
may make recommendations to the Government for promoting simplification of
methods of charge for supplies of electricity and standardisation of the system
of supply;
[*
*
*
*
*
*
*]
[*
*
*
*
*
*
*]
(2) Before the Authority exercises any control under clause (i) of sub-section (1), the area over
which and the extent to which control is intended to be exercised shall be agreed to and notified by the
Government in the Official Gazette.
[*
*
*
*
*
*
*]
12. Authority to have powers and obligations of licensee under Act IX of 1910. The
Authority shall, for the purposes of the Electricity Act, 1910 (IX of 1910), be deemed to be a licensee
and shall have all the powers and discharge all the obligations of a licensee under the said Act:
Provided that nothing in sections 3 to 11, sub-sections (2) and (3) of section 21 and sections
22, 23 and 27 or in clauses I to XII of the Schedule to the said Act relating to the duties and obligations
of a licensee shall apply to the Authority.
13. Powers regarding certain matters. (1) The Authority may take such measures and
exercise such powers as it considers necessary or expedient for the carrying out of the purposes of this
Act.
(2) Without prejudice to the generality of the power conferred by the preceding sections and
the provisions of sub-section (1) of this section, the Authority may for carrying out the purposes of
this Act__
(a)
undertake any works, incur any expenditure, procure plant, machinery and
materials required for its use and enter into and perform all such contracts as it
may consider necessary or expedient;
(b)
(c)
acquire by purchase, lease, exchange or otherwise and dispose of by sale, lease,
exchange or otherwise any land or any interest in land;
place wires, poles, wall brackets, stays, apparatus and appliances for the
transmission of electricity, or for the transmission of telegraphic or telephonic
communications necessary for the proper execution of a scheme;
(d)
direct the owners of private lands to—
(i)
carry out measures for training of streams;
Omitted by Act No. XIII of 1994, s. 5.
Omitted by Act No. XIII of 1994, s. 5.
(ii)
undertake anti-erosion operations, including conservation of forests and
re-afforestation;
(e)
restrict or prohibit by general or special order the clearing and breaking up of
land in the catchment area of any river;
(f)
direct that any work which has been required to be done by any person under
the two preceding clauses, and which remains undone, shall, after due notice to
such person and consideration of any objection raised by him, be executed by
the Authority and specify the proportion in which the risk and expense of such
work shall be borne by such person, or by any other person who, after being
given a reasonable notice and after such inquiry as the Authority considers
necessary, is held by the Authority to be responsible for the execution of such
work in whole or in part; and
(g)
seek and obtain advice and assistance in the preparation or execution of a
scheme from any local body or agency of the Government, and such local body
or agency shall give the advice and assistance sought by the Authority to the
best of its ability, knowledge and judgement:
Provided that the Authority shall pay the cost of such advice and
assistance if the giving of such advice and assistance entails additional
expenditure to the local body or the agency.
(3) The acquisition of any land or any interest in land for the Authority under this section, or
for any scheme under this Act, shall be deemed to be an acquisition for a public purpose within the
meaning of the Land Acquisition Act, 1894 (I of 1894), and the provisions of the said Act shall apply
to all such proceedings.
14. Right of entry. (1) The Chairman or any person authorised by him in writing, may enter
upon and survey any land, erect pillars for the determination of intended lines of works, make borings
and excavations and do all other acts which may be necessary for the preparation of any scheme:
Provided that when the affected land does not vest in the Authority, the power conferred by
this sub-section shall be exercised in such manner as to cause the least interference with, and the least
damage to, the rights of the owner thereof.
(2) When any person enters into or upon any land in pursuance of sub-section (1), he shall, at
the time of entering or as soon thereafter as may be practicable, pay or tender payment for all necessary
damage to be done as aforesaid, and in case of dispute as to the sufficiency of the amount so paid or
tendered, the dispute shall be referred to the Deputy Commissioner of the district whose decision shall
be final.
15. Sanction of the Government. A scheme framed and sanctioned under this Act may be
amended or modified by the Authority at any time, but if a material change is made in the scheme,
previous sanction of the Government shall be obtained.
Explanation__ An increase in the cost of the scheme by more than fifteen per cent of the
sanctioned cost, or a change in the benefit and cost ratio which either makes the cost component in the
ratio exceed the benefits or reduces the benefits component by more than fifteen per cent shall be
deemed to be a material change for the purpose of this section.
16. Arrangements with local body or other agency. (1) As soon as any scheme has been
carried out by the Authority or at a later date, the Authority may arrange by a written agreement with
a local body or other agency within whose jurisdiction any particular area covered by the scheme lies,
to take over and maintain any of the works and services in that area. If the Authority fails to obtain the
assent of such a local body or other agency, it may refer the matter to the 1[Provincial Government],
and the 2[Provincial Government] may give such directions to the local body or the other agency as it
may deem fit.
(2) The Government shall have the power to direct the Authority to hand over any scheme other
than a power scheme or the power part of a multi-purpose scheme carried out by it to any agency of
the Government or a local body. In such a case the Authority shall be entitled to receive credit to the
extent of the audited expenditure incurred by it on that scheme.
CHAPTER IV
ESTABLISHMENT
17. Employment of officers and servants. (1) The Authority may from time to time employ
such officers and servants, or appoint such experts or consultants, as it may consider necessary for the
performance of its functions, on such terms and conditions as it may deem fit 3[:]
[Provided that all persons serving in connection with the affairs of 5[a Province] in the
Electricity and Irrigation Departments shall be liable to serve under the Authority, if required to do so
by the 6[Provincial Government], on such terms and conditions as the 7[Provincial Government] may,
in consultation with the Authority, determine but shall not be entitled to any deputation allowance:
Provided further that the 8[Provincial Government] may, in relation to any such person as
aforesaid, delegate such administrative, disciplinary and financial powers to the Authority as the
[Provincial Government] may deem fit:
Provided also that the terms and conditions of service of any such person as aforesaid shall not
be varied by the Authority to his disadvantage.]
[(1A) Notwithstanding anything contained in sub-section (1) or any rules made, or orders or
instructions issued, by the Authority, or in the terms and conditions of service of any person employed
by, or serving under the Authority, the Authority may, at any time, retire or remove from its service
any person 11[after informing him in writing of the grounds on which such action is proposed to be
taken and giving him an opportunity of showing cause in writing against the action, within a period of
fourteen days.]
[Explanation I.__ For the purpose of this sub-section, ‘any person employed by, or serving
under the Authority’ includes a person referred to in the provisos to sub-section (1).
Explanation II.__ Any person referred to in the provisos to sub-section (1) who is removed or
retired from service by the Authority under this sub-section shall stand reverted to the Province to
Substituted by the Federal Adaptation of Laws Order, 1975 (President’s Order No. 4 of 1975), Art. and Sch.
Substituted by the Federal Adaptation of Laws Order, 1975 (President’s Order No. 4 of 1975), Art. and Sch.
Subs. by the West Pakistan Ordinance No. XIII of 1959, s. 4.
Added by the West Pakistan Ordinance No. XIII of 1959, s. 4.
Substituted by the Federal Adaptation of Laws Order, 1975 (President’s Order No. 4 of 1975), Art. and Sch.
Substituted by the Federal Adaptation of Laws Order, 1975 (President’s Order No. 4 of 1975), Art. and Sch.
Substituted by the Federal Adaptation of Laws Order, 1975 (President’s Order No. 4 of 1975), Art. and Sch.
Substituted by the Federal Adaptation of Laws Order, 1975 (President’s Order No. 4 of 1975), Art. and Sch.
Substituted by the Federal Adaptation of Laws Order, 1975 (President’s Order No. 4 of 1975), Art. and Sch.
Inserted by the West Pakistan Act No. LXXXIV of 1975, s. 2.
Substituted by Act No. XIII of 1994, s. 6.
Added and shall be deemed always to have been so added by West Pakistan Ordinance No. LXXII of 1979, s. 6.
which he is allocated under the Province of West Pakistan (Dissolution) Order, 1970 (P.O. No.1 of
1970).]
(1B) Service under the Authority is hereby declared to be service of Pakistan and every person
holding a post under the Authority, not being a person who is on deputation to the Authority from any
Province, shall be deemed to be a civil servant for the purposes of the Service Tribunals Act, 1973
(LXX of 1973).]
[(1C) Any order of removal or termination of service passed by the Authority, in exercise of
the powers conferred by sub-section (1A), shall not be called in question in any proceedings taken
under the Industrial Relations Ordinance, 1969 (XXIII of 1969), or the Essential Services
(Maintenance) Act, 1952 (LIII of 1952), or under any law for the time being in force, before any Court,
Tribunal or Commission and any order passed by any Court, Tribunal or Commission after the thirtieth
day of September, 1975, and before the coming into force of the West Pakistan Water and Power
Development Authority (Amendment) Ordinance, 1979, setting aside or modifying or declaring any
order of the Authority to be void and of no effect, shall stand vacated.]
[(1D) Nothing contained in the Industrial Relations Ordinance, 1969 (XXIII of 1969), shall
apply to or in relation to any person employed as a member of the security staff of the Authority for
the protection of the installations and establishments of the Authority.]
(2) The Chairman, in case of urgency, may appoint such officers and servants on such terms
and conditions as may be necessary:
Provided that every appointment made under this sub-section shall be reported to the Authority
without unreasonable delay.
(3) 3[*
*
*
*
*
*
*
*]
17A. 4[Omitted]
18. Recruitment and conditions of service and disciplinary powers. The Authority shall
prescribe the procedure for appointment, and terms and conditions of service of its officers and
servants, and shall be competent to take disciplinary action against its officers and servants.
19. Immunity of the Authority and its employees. (1) The Chairman, Members, officers and
servants of the Authority shall, when acting or purporting to act in pursuance of any of the provisions
of this Act, be deemed to be public servants within the meaning of section 21 of the Pakistan Penal
Code (XLV of 1860).
(2) No suit, prosecution or other legal proceedings shall lie against the Authority, the Chairman,
Members or officers and servants of the Authority in respect of anything done or intended to be done,
in good faith under this Act.
Added by West Pakistan Ordinance No. LXXII of 1979, s. 6.
Added by Ordinance No. XIII of 1983, s. 2.
Omitted by the West Pakistan Statutory Bodies (Appointment and Removal of Legal Advisers) Ordinance, 1965 (West Pakistan Ordinance No. XXXII
of 1965, s. 5 and Sch.
Omitted by Ordinance No. XXVII of 2000, s. 2.
20. Delegation of powers to Chairman, etc. The Authority may by general or special order
delegate to the Chairman, a Member, or officer of the Authority, any of its powers, duties or functions
under this Act subject to such conditions as it may think fit to impose.
CHAPTER V
REPORTS AND STATEMENTS
21. Submission of yearly reports and returns, etc. (1) The Authority shall submit to the
Government, as soon as possible after the end of every financial year but before the last day of
[September] next following, a report on the conduct of its affairs for that year.
(2) A copy of the report mentioned in sub-section (1), together with a copy of the audit report
referred to in section 28 shall be placed by the Government before the 2[National Assembly] 3[,] 4[and
the 5[National Assembly] shall refer the same to its Committee on public Accounts for scrutiny and
examination,]
6[
(2A) The Committee on Public Accounts shall scrutinise and examine the reports referred to
it under sub-section (2) in the same manner as, and shall in respect thereof, perform the same functions
and exercise the same powers as are required by it to be performed and exercised in respect of
appropriation accounts of the 7[Federal Government] and the report of the 8[Auditor-General] of
Pakistan thereon.]
(3) The Government may require the Authority to furnish it with__
(i)
any return, statement, estimate, statistics or other information regarding any
matter under the control of the Authority, or
(ii)
a report on any such matter, or
(iii)
a copy of any document in the charge of the Authority, and
the Authority shall comply with every such requisition.
CHAPTER VI
FINANCE
22. Authority Fund.__ (1) There shall be a fund to be known as the “Authority Fund” vested
in the Authority which shall be utilised by the Authority to meet charges in connection with its
functions under this Act including the payment of salaries and other remunerations to the Chairman
and Members of the Authority and to its officers and servants.
(2) The Authority Fund shall consist of—
(a)
grants made by the Government;
Substituted by West Pakistan Ordinance No. XII of 1960, s. 2.
Substituted by the Federal Adaptation of Laws Order, 1975 (President’s Order No. 4 of 1975), Art. and Sch.
Substituted by the West Pakistan Act No. XIII of 1967, s. 2.
Added by the West Pakistan Act No. XIII of 1967, s. 2.
Substituted by the Federal Adaptation of Laws Order, 1975 (President’s Order No. 4 of 1975), Art. and Sch.
Inserted by the West Pakistan Act No. XIII of 1967, s. 2.
Substituted by the Federal Adaptation of Laws Order, 1975 (President’s Order No. 4 of 1975), Art. and Sch.
Substituted by the Federal Adaptation of Laws Order, 1975 (President’s Order No. 4 of 1975), Art. and Sch.
(b)
loans obtained from the Government;
(c)
grants made by local bodies as required by the Government;
[(d) sale proceeds of bonds, debentures, commercial papers or other securities issued
by the Authority;]
[(dd) all sums, dividends, shares, bonds, debentures, commercial papers, securities or
any other payments received from a company or companies specified in clause
(b) of sub-section (5) of section 8;]
(e)
loans obtained by the Authority with the special or general sanction of the
Government;
(f)
foreign aid and loans obtained from the International Bank of Reconstruction
and Development or otherwise, with the sanction 3[and under the gaurantee] of,
and on such terms and conditions as may be approved by the Government; and
(g)
all other sums received by the Authority.
23. Authority to be deemed to be a local authority. 4[(1)] The Authority shall be deemed to
be a local authority under the Local Authorities Loans Act, 1914 (IX of 1914), for the purpose of
borrowing money under the said Act, and the making and execution of any scheme under this Act shall
be deemed to be a work which such authority is legally authorised to carry out.
[(2) Any sum due to the Authority shall be recoverable as arrears of land revenues.]
24. Limited liability. The liability of the Government to the creditors of the Authority shall be
limited to the extent of grants made by the Government and the loans raised by the Authority with the
sanction of the Government.
25. Rates for sale of power. (1) The Authority shall ordinarily sell power in bulk.
(2) The rates at which the Authority shall sell power shall be so fixed as to provide for meeting
the operating costs, interest charges and depreciation of assets, the redemption at due time of loans
other than those covered by depreciation, the payment of any taxes and a reasonable return on
investment.
26. Maintenance of accounts. The Authority shall maintain complete and accurate books of
accounts in such form as may be prescribed by it:
Provided that separate accounts shall be maintained for all schemes and transactions relating
to power.
27. Annual statement of accounts. In the month of 6[January] each year the Authority shall
submit to the Government for approval a statement of the estimated receipts and expenditure in respect
of the next financial year.
Substituted by Act No. XIII of 1994, s. 7.
Ins. by Act No. XIII of 1994, s. 7.
Ins. by Act No. XIII of 1994, s. 7.
Re-numbered by Act No. XIII of 1994, s. 8.
Added by Act No. XIII of 1994, s. 8.
Substituted by the West Pakistan Ordinance No. XII of 1960, s. 3.
28. Audit. The accounts of the Authority shall be audited every year by the 1[Auditor-General]
of Pakistan in such manner as may be prescribed by the Government. Copies of the audit report shall
be sent to the Authority, and, with the comments of the Authority, to the Government and shall also
be available for public inspection. The Authority shall carry out any directive issued by the
Government for rectification of an audit objection.
CHAPTER VII
29. Regulations. For the purpose of carrying into effect the provisions of this Act, the Authority
may, with the approval of the Government, frame such Regulations as it may consider necessary or
expedient.
30. Repeal. The West Pakistan Water and Power Development Authority Ordinance, 1958
(West Pakistan Ordinance No. VIII of 1958), is hereby repealed.