1
In this direction:
Act
means the
Utilities
Commission Act
;
DSM regulatory account
means the regulatory account of
the authority established under commission order G-55-95;
TMP program
means the authority's program to provide
funding to increase the electrical energy efficiency of mills that use
thermo-mechanical pulping processes.
Application
2
This direction is issued to the commission under section 3 of the
Act.
TMP program
3
1
Subject to subsection (2), in setting rates for the authority, the
commission must not disallow for any reason the recovery in rates of the costs
incurred by the authority in carrying out the TMP program.
2
The costs recovered by rates referred to in subsection (1) must not exceed
$100 million.
3
The commission must, in regard to the DSM regulatory account, allow the
authority to defer to that account the authority's costs incurred as a result of
carrying out the TMP program.