Beta
IPA patent 7.11.2-extensions-of-time---reg-5.9
IPA patent 7.11.2-extensions-of-time---reg-5.9 — IP Australia Patent Manual of Practice and Procedure – 7.11.2 Extensions of Time - Reg 5.9
Beta. Legal information, not legal advice. LEGALDIGM is not a law firm. Check the official source for the current text.
Also in this Chapter:
7.11.1 Extensions of Time - Section 223
7.11.3 Restoration of the Right of Priority under the PCT
Sub-chapters:
7.11.2.1 Requesting an Extension of Time
7.11.2.2 Application of the Law
7.11.2.3 Justification for the Extension
7.11.2.4 Discretionary Matters
7.11.2.5 Period of an Extension
7.11.2.6 A Hearing in Relation to an Extension
7.11.2.7 Parties Involved in Negotiations
7.11.2.8 Review of a Decision to Grant or Refuse an Extension
7.11.2.9 "Out of Time" Evidence
Key Legislation:
Patents Regulations:
reg 5.8 Evidentiary periods
reg 5.9 Extension of time for filing evidence
reg 5.12 Practice and procedure
reg 5.17 Dismissal on request
reg 5.22 Commissioner may give directions
reg 23.36 Amendments made by Intellectual Property Legislation Amendment (Raising the Bar) Regulation 2013 (No. 1)
Chapter 5 Opposition
Schedule 7 Fees
Related Chapters:
7.3.1 Directions in Opposition Proceedings
In this topic:
Relevant Legislation
The Regulations
Introduction
What periods can be extended under reg 5.9?
The Regulations
Chapter 5 Opposition
Schedule 7 Fees
Introduction
Under reg 5.9 , the Commissioner may extend the time to file evidence in support, answer or reply, in a substantive opposition, either on the request of a party in writing, or on the Commissioner’s own initiative.
Reg 5.9 was introduced following amendments to Chapter 5 of the Regulations that took effect on 15 April 2013 to address the significant narrowing of the Commissioner’s discretion to disallow extensions under the previous regime (see Explanatory Statement ).
What periods can be extended under reg 5.9?
Regulation 5.9 allows the Commissioner to extend the time for an "evidentiary period" specified in reg 5.8 (see reg 23.36(2) item 2 ).
Consequently, the time for filing evidence in support, evidence in answer or evidence in reply can be extended under reg 5.9 in substantive oppositions. Regulation 5.9 cannot be used to extend the time for requesting dismissal of an opposition (under reg 5.17 ).
Procedural oppositions do not have fixed evidentiary periods under reg 5.8 , so these periods cannot be extended under reg 5.9 . Instead, these matters are managed by directions under regs 5.12 or 5.22 (see 7.3.1 Directions in Opposition Proceedings ).